Blackwell Public Schools announced the Blackwell 2021 Bond Proposal set to vote on November 9th, 2021.
Blackwell Board of Education is presenting this bond issue to replace the Elementary School Bond; which expires in June of 2022.
It will be in the amount of $23,550,000.00 for 15 years. School Bonds are based on property taxes that is in the Blackwell School District only, not local sales tax.
Blackwell Board of Education is presenting this bond issue to replace the Elementary School Bond; which expires in June of 2022. It will be in the amount of $23,550,000.00 for 15 years. School Bonds are based on property taxes that is in the Blackwell School District only, not local sales tax. The following figures are based on the 2020 property taxes. This bond issue would raise the district mileage rate to 32.02. Our district’s current millage rate is 20.91. In 2007 when the elementary school bond passed it raised our millage rate to 34.86. This bond would be a little smaller increase than the 2007 school bond tax increase. It would be a 11.88% tax increase. For every $100.00 of property taxes paid, your property taxes would go up $11.88.
For Example: if your taxes were $600.00 you would now pay $671.28 $600 X .1188 = $71.28 + $600 = $671.28. This would be an increase of $5.94 per month on your property taxes. To view your taxes – go to the Kay County treasurer website, https://oktaxrolls.com/county/
IMPROVEMENTS:
High School Building – Built in 1962
New Secure Vestibule Entry and Office Suite
New Kitchen
ADA Accessible Library Renovations
ADA Accessible Storm Shelter on the Ground Floor
ADA Accessible Restroom Renovations
Modernize All Classrooms (Solid Classroom Hallway Walls) Remove all Hallway Glass
Open Up Corridors
New HVAC
New Fire Suppression System
New Electrical
New Flooring
New LED Lighting
New Exterior Entrances
New Paint
New Window Film on the Study Center Windows, Making the Glass More Difficult to See In
New Ceiling in Study Center
New Lockers
New Entry Parking
Auditorium Building – Built in 1968
ADA Accessible Restroom Renovations
New Store Front
New Doors
Demo Brick Planters and Pavers
New Paint and Ceilings in Lobby
New Carpet and Seating in Auditorium
New Stage Sound and Lighting
New House Lighting
New Paint
New HVAC
Band & Vocal Rooms – Built in 1968
New HVAC
New Doors
New Instrument Storage
New Flooring
ADA Accessible Restrooms Renovations
New Ceiling and Lights
New Paint
VoAg – Wood Shop – Built in 1970
New Front Exterior Doors and Windows
New Flooring
New Ceilings
New Paint
Practice Gym – Built in 1968
New Entry Canopy with New Vestibule
New Interior and Exterior Paint
New Front Concrete Sidewalk
Heating Improvements
Football Facilities (South Side) – Built Around 1952
New ADA Access Ramp
New ADA Seating Platform
New All Aluminum Seating
New Press Box
New Building Which Would Consist of ADA Restrooms, Concession Stand and Football Locker Room
Roofing
High School B and C wing
Auditorium High Roof
Vo-Ag – Wood Shop
These are the remaining roofs that were not replaced 3 years ago. Everything on campus will now have a roof that has a warranty on it.
Middle School
HVAC Improvements